The Study is scheduled to begin towards the end of 2011 and proceed through February, 2014. Please see below for a tentative project schedule. This schedule will be routinely updated as more detailed scheduling information becomes available.
Project Tasks
Refine Study Goals and Scope ............................................. .November, 2011
Public Outreach .....................................................................Ongoing
Municipal Advisory Group (MAG) Meeting .................August, 22, 2012
Focus Group Meetings/Workshops (3).........................October, 2012 - January, 2013
Existing Conditions Report .....................................................June, 2013
Selection of 3 Station Areas ...................................................June, 2013
Public Workshops ..................................................................October - November, 2013
Final Feasibility Report ..........................................................January - February, 2014
Total Project Duration........................................................24-27 months
Acting Commissioner
1194 Prospect Avenue
Westbury, NY 11590-2723
Illicit Discharges: 516-571-7535
Road Maintenance: 516-571-6900
Traffic Signals: 516-572-0465
Mosquito Control: 516-571-6900
SUEZ Emergency Hotline: 866-224-8508 (For all sewer related issues.)